Coaltech Research Association

Review of Current and Expected Underground Coal Mining Methods and an Evaluation of the Best Practices Associated with These

André William Dougall

Review of underground coal production systems in South Africa set against practice in Australia, China and the United States, with guidance on equipment choice and section planning.

by André William Dougall | 2010

What this report found

South African underground sections average about 60 000 t a month, against 130 000 to 160 000 t for single pass bolter miner units on continuous haulage, while the better sections target 1.4 to 1.6 Mt a year. Australian longwalls deliver 5 to 7 Mt a year from one face, compared with 3 to 5 Mt at the two local wall operations.

R1500,00

Description

Related Products

T F Ngobeni

Transformation of the Coal Mining Procurement Supply Chain

2004

Review of preferential procurement and small supplier development at South African coal producers, based on interviews with procurement staff, suppliers and accreditation agencies, with recommendations for management.

What this report foundThree modes of intervention were found in coal company procurement: preferential procurement rules, segmentation of goods and services by suitability for...

R1500,00

R1500,00

What this report found

Three modes of intervention were found in coal company procurement: preferential procurement rules, segmentation of goods and services by suitability for transformation, and support programmes for small suppliers. Progress stalled where supplier development was handled by staff carrying other duties, since work not tied to production loses time and has no target. The remedy proposed is procurement targets linked down through commercial and production management.

Recharge in Rehabilitated Opencast Collieries

Eelco Lukas

2019

Groundwater levels and pumping records from five rehabilitated opencast pits at South African collieries, for hydrogeologists and closure planners estimating post-mining water balances.

What this report foundRecharge factors of 23.5 per cent and 12.9 per cent were calculated at the two rehabilitated pits with complete data.

R1500,00

R1500,00

Eelco Lukas

What this report found

Recharge factors of 23.5 per cent and 12.9 per cent were calculated at the two rehabilitated pits with complete data. The higher value reflected surface drainage towards the pit centre and eroded topsoil; the lower one, a deep pit floor with well compacted spoil and intact cover. The rates are site specific and no generic formula could be derived.