TRI-FLO™ Tests Conducted at South Witbank Coal Mine
200317 pages
Trial of an imported dense medium separator installed in a fine coal pilot plant at a Witbank mine, for plant designers weighing alternatives to cyclones.
The separator handled fine coal and produced a 28 MJ/kg product, but its measured separation efficiency was lower than that of conventional dense medium cyclones and it was harder to operate. Two efficiency tests produced no evidence that the unit outperforms cyclones on fine coal, so cyclones were recommended when the plant was rebuilt at its next site.
Contents
- EXCUTIVE SUMMARY2
- INTRODUCTION4
- OPERATION OF THE TRI-FLOWTM DENSE-MEDIUM SEPARATOR4
- TEST WORK8
- EFFICIENCY TESTS10
- COMMENTS14
- CONCLUSION15
- RECOMMENDATION15
How it opens
Jim Harrison Design Associates (JHDA), the company that will be marketing the Tri-floTM dense-medium separator in South Africa on behalf of Ecomin in Italy, requested permission to test a Tri-flo unit in the Coaltech 2020 fine coal dense-medium plant at South Witbank Coal Mine (SWC) so as to ascertain whether the Tri-flo unit would be suited to processing fine coal.
How it concludes
R1500,00
Description
Related Products
Models for Predicting Methane Gas Release from Coal Seams
2005
Emission factors and calculation models for national greenhouse gas reporting, built from mine seam gas measurements and ventilation sampling, for environmental staff and inventory compilers.
What this report foundEmission factors derived from measured South African seam gas data give simple models for methane released by underground mining, surface mining and coal after...
R1500,00
Emission factors derived from measured South African seam gas data give simple models for methane released by underground mining, surface mining and coal after mining. Applied across the industry they put total methane emissions at 52 000 to 93 000 tons a year. The models follow the IPCC Tier 2 approach using country specific factors.
Application of EARTH Ion Exchange Technology to Process RO (Hipro) Brine from eWRP
2010
Pilot trial on brine from a working water reclamation plant on the Mpumalanga coalfield, the first of four studies testing ion exchange on coal mine liquors.
What this report foundIon exchange applied to brine from a three stage reverse osmosis plant at eMalahleni converted the brine entirely into saleable fertiliser and explosives...
R1500,00
Ion exchange applied to brine from a three stage reverse osmosis plant at eMalahleni converted the brine entirely into saleable fertiliser and explosives feedstock, and recovered close to half of the water the reverse osmosis stage leaves behind. On this basis the existing brine pond and the two planned for the plant expansion would not be needed.